Define initial settings for a scheduling period

Define the initial settings for a scheduling period, including the number of weeks, start date, and the data on which the scheduling period is based.

Before you begin

Create a campaign

Procedure 

  1. From the left side under Campaign Name, select the campaign for which you want to create a scheduling period.

  2. Select Create Scheduling Period.

  3. For Number of Weeks, specify the number of weeks in the scheduling period.

  4. For Start Date, specify the start date of the scheduling period.

  5. Under Initialization Options, specify how to create the data for the scheduling period:

    You should only select this parameter if you want to copy work rule exceptions made for the selected scheduling period. If you want to use the default organizational work rule settings defined in the Work Administration module, do not select this option.

  6. Select Save.

    The scheduling period appears under the selected campaign. You are now ready to configure the general settings and hours of operation for the scheduling period.

What to do next 

Configure general settings and hours of operation

Scheduling period settings